Quote from Suzanne Kidd below, two things appear very strange. They are appointing after tender but have no timescale plan ?
They have appointed after tender but have no details ?
Funny way of gan-on......
Carlisle United are set to step up their flood recovery work having appointed two contractors to carry out the next stage of repairs to Brunton Park.
Phase two of the rebuilding at United's stadium will be done by Esh Border Construction and Story Contracting.
They have been appointed after a tendering process and the work - intended to be completed in time for next season - will be divided between the two firms.
While phase one concerned short-term work that enabled Carlisle to return to Brunton Park after the December 5 floods, phase two will focus on many other areas of the stadium and surroundings.
The Blues' finance director Suzanne Kidd said it was a key period in restoring the ground after the devastation of Storm Desmond.
"It's getting under way now," she said.
"We've appointed our contractors and we just need a timescale plan now.
"We are going to split the work. Esh are going to do the houses, study centre, Neil Centre and the Pioneer Foods [east] Stand, and Story will be doing the external areas and west stand, which incorporates the offices, up to the top of the Paddock terrace and down to the changing rooms.
"As for the public areas and concourses, we have to wait until after the two remaining important home games - and hopefully the play-offs.
"So we go with the calendar and hopefully everything will be back up and running for the start of next season."
Kidd said some of United's facilities would be "modernised" as a result of the work but some of the details were yet to be finalised.
She added: "We have had some different plans drawn up and we need to present them to the board and get approval for them, to see what direction we move in."
The club is working towards July 31 as a deadline for the work, with the 2016/17 season set to start on the weekend of August 6.
United, meanwhile, re-opened their family zone in the Pioneer Stand on Saturday after a £15,000 refurbishment paid for by the Football League's title sponsor SkyBet.